BetaActiveOtherMISOLBNL
1 MW generation in MN · In queue since October 2012 · Proposed COD April 2013
1 MW
Capacity
1
Components
Other
13y 5m
In Queue
IA Executed
IA Status
COD target: 2013
Interconnection Timeline
Total Duration
6 months
Schedule
158 months past proposed COD
Construction75%
Queue EntryOct 30, 2012
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–36 months
Commercial Operation
Proposed COD: 2013-04-01
Project Details
State
MN
County
—
Region
MISO
Developer
—
Utility
—
Entity
MISO
Point of Interconnection
Melrose East 69kV Substation
Data Source
LBNL
No news available for this project.