BetaActiveWindMISOLBNL + Live
164.1 MW generation in Louisa, IA · In queue since September 2022 · Proposed COD January 2025
164.1 MW
Capacity
1
Components
Wind
3y 6m
In Queue
Cluster Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 4m
Schedule
14 months past proposed COD
Impact Study25%
Queue EntrySep 15, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-01-31
Project Details
State
IA
County
Louisa
Region
MISO
Developer
—
Utility
ITC MIDWEST
Entity
MISO
Point of Interconnection
Denmark 161kV - Newport 161kV
Data Source
LBNL + Live
No news available for this project.