BetaActiveBatteryMISOLBNL + Live
100 MW storage in Ingham, MI · In queue since August 2023 · Proposed COD September 2026
100 MW
Capacity
1
Components
Battery
2y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 1m
In Study38%
Queue EntryAug 28, 2023
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-09-01
Project Details
State
MI
County
Ingham
Region
MISO
Developer
—
Utility
METC
Entity
MISO
Point of Interconnection
DELHI to TOMPKINS 138kV
Data Source
LBNL + Live