— Project Summary

Queue ID
MISO-J2545
Capacity
200 MW
Technology
Battery
Status
active
Location
Buchanan, IA
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveBatteryMISOLBNL + Live

200 MW storage in Buchanan, IA · In queue since September 2022 · Proposed COD November 2026

200 MW

Capacity

1

Components

Battery

3y 6m

In Queue

Cluster Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 2m

Impact Study25%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-11-01

Project Details

State

IA

County

Buchanan

Region

MISO

Developer

Utility

ITC MIDWEST

Entity

MISO

Point of Interconnection

Duane Arnold 345 kV

Data Source

LBNL + Live

No news available for this project.