— Project Summary

Queue ID
MISO-J2541
Capacity
50 MW
Technology
Solar
Status
active
Location
Graves, KY
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveSolarMISOLBNL + Live

50 MW generation in Graves, KY · In queue since September 2022 · Proposed COD March 2026

50 MW

Capacity

1

Components

Solar

3y 6m

In Queue

Cluster Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 6m

Schedule

1 months past proposed COD

Impact Study25%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-03-01

Project Details

State

KY

County

Graves

Region

MISO

Developer

Utility

BIG RIVERS ELECTRIC CORPORATION

Entity

MISO

Point of Interconnection

Bryan Road

Data Source

LBNL + Live

No news available for this project.