— Project Summary

Queue ID
MISO-J2524
Capacity
200 MW
Technology
Solar
Status
active
Location
Stoddard, MO
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveSolarMISOLBNL + Live

200 MW generation in Stoddard, MO · In queue since September 2022 · Proposed COD November 2026

200 MW

Capacity

1

Components

Solar

3y 6m

In Queue

Cluster Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 2m

Impact Study25%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-11-01

Project Details

State

MO

County

Stoddard

Region

MISO

Developer

Utility

AMEREN MISSOURI

Entity

MISO

Point of Interconnection

5STODDARD - 5MORLEY (AECI) 161kV

Data Source

LBNL + Live