— Project Summary

Queue ID
MISO-J2523
Capacity
250 MW
Technology
Solar
Status
active
Location
Independence, AR
Region
MISO
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarMISOLBNL + Live

250 MW generation in Independence, AR · In queue since September 2022 · Proposed COD November 2026

250 MW

Capacity

1

Components

Solar

3y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 2m

In Study38%
Queue EntrySep 14, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-11-01

Project Details

State

AR

County

Independence

Region

MISO

Developer

Utility

ENTERGY ARKANSAS

Entity

MISO

Point of Interconnection

INDEPENDENCE-ISES 500kV Substation

Data Source

LBNL + Live

No news available for this project.