— Project Summary

Queue ID
MISO-J2496
Capacity
400 MW
Technology
Battery
Status
active
Location
White, IN
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveBatteryMISOLBNL + Live

400 MW storage in White, IN · In queue since September 2022 · Proposed COD March 2026

400 MW

Capacity

1

Components

Battery

3y 6m

In Queue

Cluster Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 6m

Schedule

1 months past proposed COD

Impact Study25%
Queue EntrySep 13, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-03-07

Project Details

State

IN

County

White

Region

MISO

Developer

Utility

NORTHERN INDIANA PUBLIC SERVICE COMPANY

Entity

MISO

Point of Interconnection

Reynolds 345 kV Substation

Data Source

LBNL + Live

No news available for this project.