— Project Summary

Queue ID
MISO-J2446
Capacity
300 MW
Technology
Solar
Status
active
Location
Dunn, WI
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveSolarMISOLBNL + Live

300 MW generation in Dunn, WI · In queue since September 2022 · Proposed COD September 2027

300 MW

Capacity

1

Components

Solar

3y 6m

In Queue

Cluster Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5 years

Impact Study25%
Queue EntrySep 12, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-09-01

Project Details

State

WI

County

Dunn

Region

MISO

Developer

Utility

NORTHERN STATES POWER COMPANY

Entity

MISO

Point of Interconnection

Allen S King 345kV - Eau Claire 345 kV

Data Source

LBNL + Live