— Project Summary

Queue ID
MISO-J2436
Capacity
300 MW
Technology
Wind
Status
active
Location
Webster, IA
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveWindMISOLBNL + Live

300 MW generation in Webster, IA · In queue since September 2022 · Proposed COD October 2030

300 MW

Capacity

1

Components

Wind

3y 6m

In Queue

Cluster Study

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

8y 1m

Impact Study25%
Queue EntrySep 12, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-10-01

Project Details

State

IA

County

Webster

Region

MISO

Developer

Utility

CEDAR FALLS MUNICIPAL ELECTRIC UTILITY

Entity

MISO

Point of Interconnection

Webster-Lehigh 345kV

Data Source

LBNL + Live

No news available for this project.