— Project Summary

Queue ID
MISO-J2397
Capacity
160 MW
Technology
Solar+Battery
Status
active
Location
Calhoun, AR
Region
MISO
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryMISOLBNL + Live

160 MW hybrid in Calhoun, AR · In queue since September 2022 · Proposed COD May 2025

160 MW

Capacity

1

Components

Solar

3y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 8m

Schedule

10 months past proposed COD

In Study38%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-05-31

Project Details

State

AR

County

Calhoun

Region

MISO

Developer

Utility

ENTERGY ARKANSAS

Entity

MISO

Point of Interconnection

SHERIDAN EHV - EL DORADO EHV 500 kV (851.1)

Data Source

LBNL + Live

No news available for this project.