— Project Summary

Queue ID
MISO-J2388
Capacity
200 MW
Technology
Solar+Battery
Status
active
Location
Macon, IL
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveSolarBatteryMISOLBNL + Live

200 MW hybrid in Macon, IL · In queue since September 2022 · Proposed COD September 2026

200 MW

Capacity

1

Components

Solar

3y 6m

In Queue

Cluster Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4 years

Impact Study25%
Queue EntrySep 15, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-09-30

Project Details

State

IL

County

Macon

Region

MISO

Developer

Utility

AMEREN TRANSMISSION COMPANY OF ILLINOIS

Entity

MISO

Point of Interconnection

Faraday 345kV

Data Source

LBNL + Live