— Project Summary

Queue ID
MISO-J2334
Capacity
195 MW
Technology
Solar
Status
active
Location
Montgomery, IL
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveSolarMISOLBNL + Live

195 MW generation in Montgomery, IL · In queue since September 2022 · Proposed COD September 2027

195 MW

Capacity

1

Components

Solar

3y 6m

In Queue

Cluster Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5 years

Impact Study25%
Queue EntrySep 14, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-09-01

Project Details

State

IL

County

Montgomery

Region

MISO

Developer

Utility

AMEREN ILLINOIS

Entity

MISO

Point of Interconnection

Redhawk Substation 138kV

Data Source

LBNL + Live

No news available for this project.