— Project Summary

Queue ID
MISO-J2322
Capacity
200 MW
Technology
Solar
Status
active
Location
Evangeline Parish, LA
Region
MISO
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarMISOLBNL + Live

200 MW generation in Evangeline Parish, LA · In queue since May 2022 · Proposed COD July 2025

200 MW

Capacity

1

Components

Solar

3y 10m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 2m

Schedule

9 months past proposed COD

In Study38%
Queue EntryMay 17, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-07-02

Project Details

State

LA

County

Evangeline Parish

Region

MISO

Developer

Utility

CLECO POWER

Entity

MISO

Point of Interconnection

Pine Prairie to Coughlin 138 kV

Data Source

LBNL + Live

No news available for this project.