BetaActiveSolarMISOLBNL + Live
77.5 MW generation in Dickinson, MI · In queue since September 2021 · Proposed COD September 2023
77.5 MW
Capacity
1
Components
Solar
4y 6m
In Queue
Cluster Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2 years
Schedule
31 months past proposed COD
Impact Study25%
Queue EntrySep 16, 2021
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-09-15
Project Details
State
MI
County
Dickinson
Region
MISO
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Point of Interconnection
Nordic 138kV Substation
Data Source
LBNL + Live
No news available for this project.