BetaActiveSolarMISOLBNL + Live
100 MW generation in Murray, MN · In queue since September 2021 · Proposed COD October 2024
100 MW
Capacity
1
Components
Solar
4y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 1m
Schedule
17 months past proposed COD
In Study38%
Queue EntrySep 7, 2021
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-10-30
Project Details
State
MN
County
Murray
Region
MISO
Developer
—
Utility
NORTHERN STATES POWER COMPANY
Entity
MISO
Point of Interconnection
Chanarambie - Ellsborough 115 kV line
Data Source
LBNL + Live
No news available for this project.