— Project Summary

Queue ID
MISO-J2309
Capacity
100 MW
Technology
Solar
Status
active
Location
Murray, MN
Region
MISO
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarMISOLBNL + Live

100 MW generation in Murray, MN · In queue since September 2021 · Proposed COD October 2024

100 MW

Capacity

1

Components

Solar

4y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 1m

Schedule

17 months past proposed COD

In Study38%
Queue EntrySep 7, 2021

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-10-30

Project Details

State

MN

County

Murray

Region

MISO

Developer

Utility

NORTHERN STATES POWER COMPANY

Entity

MISO

Point of Interconnection

Chanarambie - Ellsborough 115 kV line

Data Source

LBNL + Live

No news available for this project.