— Project Summary

Queue ID
MISO-J2304
Capacity
400 MW
Technology
Battery
Status
active
Location
Columbia, WI
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveBatteryMISOLBNL + Live

400 MW storage in Columbia, WI · In queue since December 2021 · Proposed COD April 2024

400 MW

Capacity

1

Components

Battery

4y 3m

In Queue

Cluster Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

2y 4m

Schedule

24 months past proposed COD

Impact Study25%
Queue EntryDec 2, 2021

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-04-15

Project Details

State

WI

County

Columbia

Region

MISO

Developer

Utility

AMERICAN TRANSMISSION COMPANY

Entity

MISO

Point of Interconnection

Columbia - Rockdale 345.0kV

Data Source

LBNL + Live

No news available for this project.