70 MW generation in MI · In queue since September 2011 · Proposed COD May 2018
70 MW
Capacity
1
Components
Hydro
14y 6m
In Queue
IA Executed
IA Status
COD target: 2018
Interconnection Timeline
Total Duration
6y 8m
Schedule
95 months past proposed COD
Construction75%
Queue EntrySep 27, 2011
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–36 months
Commercial Operation
Proposed COD: 2018-05-25
Project Details
State
MI
County
—
Region
MISO
Developer
—
Utility
—
Entity
MISO
Point of Interconnection
Ludington Substation
Data Source
LBNL