BetaActiveSolarMISOLBNL + Live
175 MW generation in Audrain, MO · In queue since March 2022 · Proposed COD June 2025
175 MW
Capacity
1
Components
Solar
4 years
In Queue
Cluster Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 3m
Schedule
10 months past proposed COD
Impact Study25%
Queue EntryMar 24, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-06-01
Project Details
State
MO
County
Audrain
Region
MISO
Developer
—
Utility
AMEREN MISSOURI
Entity
MISO
Point of Interconnection
J956 collector substation (345kv; same ownership as other project connecting to sub, so no consent a
Data Source
LBNL + Live
No news available for this project.