— Project Summary

Queue ID
MISO-J2288
Capacity
175 MW
Technology
Solar
Status
active
Location
Audrain, MO
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveSolarMISOLBNL + Live

175 MW generation in Audrain, MO · In queue since March 2022 · Proposed COD June 2025

175 MW

Capacity

1

Components

Solar

4 years

In Queue

Cluster Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 3m

Schedule

10 months past proposed COD

Impact Study25%
Queue EntryMar 24, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-06-01

Project Details

State

MO

County

Audrain

Region

MISO

Developer

Utility

AMEREN MISSOURI

Entity

MISO

Point of Interconnection

J956 collector substation (345kv; same ownership as other project connecting to sub, so no consent a

Data Source

LBNL + Live

No news available for this project.