198 MW storage in IN · In queue since March 2022 · Proposed COD June 2023
198 MW
Capacity
1
Components
Battery
4 years
In Queue
Cluster Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
1y 3m
Schedule
34 months past proposed COD
Impact Study25%
Queue EntryMar 28, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-06-01
Project Details
State
IN
County
—
Region
MISO
Developer
—
Utility
DUKE ENERGY INDIANA
Entity
MISO
Point of Interconnection
GREENWOOD CLARK TOWNSHIP
Data Source
LBNL + Live