BetaActiveSolarBatteryMISOLBNL + Live
250 MW hybrid in Clinton, IA · In queue since July 2021 · Proposed COD September 2024
250 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 2m
Schedule
19 months past proposed COD
In Study38%
Queue EntryJul 22, 2021
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-09-01
Project Details
State
IA
County
Clinton
Region
MISO
Developer
—
Utility
ITC MIDWEST
Entity
MISO
Point of Interconnection
161kV East Calamus Substation
Data Source
LBNL + Live
No news available for this project.