BetaActiveSolarMISOLBNL + Live
300 MW generation in Sullivan, IN · In queue since August 2021 · Proposed COD October 2024
300 MW
Capacity
1
Components
Solar
4y 7m
In Queue
Cluster Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 2m
Schedule
17 months past proposed COD
Impact Study25%
Queue EntryAug 16, 2021
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-10-30
Project Details
State
IN
County
Sullivan
Region
MISO
Developer
—
Utility
HOOSIER ENERGY
Entity
MISO
Point of Interconnection
Merom 345 kV
Data Source
LBNL + Live