— Project Summary

Queue ID
MISO-J2265
Capacity
200 MW
Technology
Solar+Battery
Status
active
Location
Bollinger, MO
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveSolarBatteryMISOLBNL + Live

200 MW hybrid in Bollinger, MO · In queue since September 2021 · Proposed COD February 2024

200 MW

Capacity

1

Components

Solar

4y 6m

In Queue

Cluster Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

2y 5m

Schedule

26 months past proposed COD

Impact Study25%
Queue EntrySep 7, 2021

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-02-15

Project Details

State

MO

County

Bollinger

Region

MISO

Developer

Utility

AMEREN MISSOURI

Entity

MISO

Point of Interconnection

St. Francois (Bus #345773) - Lutesville (Bus #344974) 345 kV Line

Data Source

LBNL + Live