BetaActiveWindMISOLBNL + Live
251.5 MW generation in Presque Isle, MI · In queue since October 2021 · Proposed COD July 2023
251.5 MW
Capacity
1
Components
Wind
4y 5m
In Queue
Cluster Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
1y 9m
Schedule
32 months past proposed COD
Impact Study25%
Queue EntryOct 7, 2021
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-07-31
Project Details
State
MI
County
Presque Isle
Region
MISO
Developer
—
Utility
METC
Entity
MISO
Point of Interconnection
Port Calcite- Hammond Bay 138 kV
Data Source
LBNL + Live
No news available for this project.