200 MW generation in Stutsman, ND · In queue since November 2021 · Proposed COD April 2024
200 MW
Capacity
1
Components
Wind
4y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 5m
Schedule
24 months past proposed COD
In Study38%
Queue EntryNov 1, 2021
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-04-01
Project Details
State
ND
County
Stutsman
Region
MISO
Developer
—
Utility
MONTANA-DAKOTA UTILITIES CO.
Entity
MISO
Point of Interconnection
Ellendale sub 345 kV (46.009357, -98.567742)
Data Source
LBNL + Live