BetaActiveSolarMISOLBNL + Live
200 MW generation in Sullivan, IN · In queue since March 2022 · Proposed COD April 2025
200 MW
Capacity
1
Components
Solar
4 years
In Queue
Cluster Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 1m
Schedule
12 months past proposed COD
Impact Study25%
Queue EntryMar 24, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-04-01
Project Details
State
IN
County
Sullivan
Region
MISO
Developer
—
Utility
DUKE ENERGY INDIANA
Entity
MISO
Point of Interconnection
Merom Gibson 345kV line Tap
Data Source
LBNL + Live
No news available for this project.