BetaActiveSolarMISOLBNL + Live
89 MW generation in Trempealeau, WI · In queue since November 2021 · Proposed COD October 2024
89 MW
Capacity
1
Components
Solar
4y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 11m
Schedule
17 months past proposed COD
In Study38%
Queue EntryNov 30, 2021
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-10-31
Project Details
State
WI
County
Trempealeau
Region
MISO
Developer
—
Utility
DAIRYLAND POWER COOPERATIVE
Entity
MISO
Point of Interconnection
N-3 Bridge Creek to Independence 69kV Line [See Operating Agreement 5 for Correction Discussion]
Data Source
LBNL + Live
No news available for this project.