— Project Summary

Queue ID
MISO-J2215
Capacity
300 MW
Technology
Battery
Status
active
Location
Lake, IN
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveBatteryMISOLBNL + Live

300 MW storage in Lake, IN · In queue since March 2022 · Proposed COD September 2024

300 MW

Capacity

1

Components

Battery

4 years

In Queue

Cluster Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

2y 6m

Schedule

18 months past proposed COD

Impact Study25%
Queue EntryMar 25, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-09-30

Project Details

State

IN

County

Lake

Region

MISO

Developer

Utility

NORTHERN INDIANA PUBLIC SERVICE COMPANY

Entity

MISO

Point of Interconnection

SCHAHFER GEN STA - ST. JOHN 345.0kV

Data Source

LBNL + Live