BetaActiveWindMISOLBNL + Live
15.6 MW generation in Mcdonough, IL · In queue since August 2021 · Proposed COD December 2019
15.6 MW
Capacity
1
Components
Wind
4y 7m
In Queue
Cluster Study
IA Status
COD target: 2019
Interconnection Timeline
Total Duration
4y 7m
Schedule
77 months past proposed COD
Impact Study25%
Queue EntryAug 17, 2021
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2019-12-01
Project Details
State
IL
County
Mcdonough
Region
MISO
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Point of Interconnection
Hornsby Switching Station
Data Source
LBNL + Live
No news available for this project.