— Project Summary

Queue ID
MISO-J2171
Capacity
500 MW
Technology
Solar
Status
active
Location
Perry, IL
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveSolarWindMISOLBNL + Live

500 MW hybrid in Perry, IL · In queue since March 2022 · Proposed COD May 2024

500 MW

Capacity

1

Components

Solar

4 years

In Queue

Cluster Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

2y 2m

Schedule

23 months past proposed COD

Impact Study25%
Queue EntryMar 25, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-05-01

Project Details

State

IL

County

Perry

Region

MISO

Developer

Utility

AMEREN ILLINOIS

Entity

MISO

Point of Interconnection

Aster to Commodore

Data Source

LBNL + Live

No news available for this project.