BetaActiveSolarMISOLBNL + Live
150 MW generation in Johnson, IL · In queue since June 2022 · Proposed COD May 2024
150 MW
Capacity
1
Components
Solar
3y 9m
In Queue
Cluster Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
1y 11m
Schedule
22 months past proposed COD
Impact Study25%
Queue EntryJun 28, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-05-31
Project Details
State
IL
County
Johnson
Region
MISO
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Point of Interconnection
Massac - Jordan 345kV
Data Source
LBNL + Live
No news available for this project.