BetaActiveSolarMISOLBNL + Live
150 MW generation in New Madrid, MO · In queue since March 2022 · Proposed COD May 2024
150 MW
Capacity
1
Components
Solar
4 years
In Queue
Cluster Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 2m
Schedule
22 months past proposed COD
Impact Study25%
Queue EntryMar 28, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-05-31
Project Details
State
MO
County
New Madrid
Region
MISO
Developer
—
Utility
AMEREN MISSOURI
Entity
MISO
Point of Interconnection
Reelfoot - Sikeston 161 kV Line MTEP Project 19852 Facility ID 26201
Data Source
LBNL + Live
No news available for this project.