— Project Summary

Queue ID
MISO-J2139
Capacity
250 MW
Technology
Solar+Battery
Status
active
Location
Livingston, MI
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveSolarBatteryMISOLBNL + Live

250 MW hybrid in Livingston, MI · In queue since September 2021 · Proposed COD September 2024

250 MW

Capacity

1

Components

Solar

4y 6m

In Queue

Cluster Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3 years

Schedule

19 months past proposed COD

Impact Study25%
Queue EntrySep 2, 2021

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-09-01

Project Details

State

MI

County

Livingston

Region

MISO

Developer

Utility

ITC

Entity

MISO

Point of Interconnection

345kV Blackfoot-Madrid Line

Data Source

LBNL + Live

No news available for this project.