BetaActiveSolarMISOLBNL + Live
190.9 MW generation in Iroquois, IL · In queue since March 2022 · Proposed COD September 2024
190.9 MW
Capacity
1
Components
Solar
4 years
In Queue
Cluster Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 6m
Schedule
19 months past proposed COD
Impact Study25%
Queue EntryMar 23, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-09-01
Project Details
State
IL
County
Iroquois
Region
MISO
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Point of Interconnection
Gilman substation 138 kV
Data Source
LBNL + Live
No news available for this project.