— Project Summary

Queue ID
MISO-J2131
Capacity
150 MW
Technology
Solar
Status
active
Location
Jasper, IL
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveSolarMISOLBNL + Live

150 MW generation in Jasper, IL · In queue since August 2021 · Proposed COD April 2027

150 MW

Capacity

1

Components

Solar

4y 7m

In Queue

Cluster Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 8m

Impact Study25%
Queue EntryAug 16, 2021

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-04-15

Project Details

State

IL

County

Jasper

Region

MISO

Developer

Utility

AMEREN ILLINOIS

Entity

MISO

Point of Interconnection

7CASEY - 7NEWTON 345.0kV

Data Source

LBNL + Live