BetaActiveSolarMISOLBNL + Live
150 MW generation in Jasper, IL · In queue since August 2021 · Proposed COD April 2027
150 MW
Capacity
1
Components
Solar
4y 7m
In Queue
Cluster Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 8m
Impact Study25%
Queue EntryAug 16, 2021
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-04-15
Project Details
State
IL
County
Jasper
Region
MISO
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Point of Interconnection
7CASEY - 7NEWTON 345.0kV
Data Source
LBNL + Live
No news available for this project.