BetaActiveSolarBatteryMISOLBNL + Live
150 MW hybrid in Barry, MI · In queue since August 2021 · Proposed COD April 2024
150 MW
Capacity
1
Components
Solar
4y 7m
In Queue
Cluster Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 8m
Schedule
24 months past proposed COD
Impact Study25%
Queue EntryAug 26, 2021
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-04-15
Project Details
State
MI
County
Barry
Region
MISO
Developer
—
Utility
WOLVERINE POWER SUPPLY COOPERATIVE
Entity
MISO
Point of Interconnection
Bradley 138 kV Substation
Data Source
LBNL + Live
No news available for this project.