BetaActiveBatteryMISOLBNL + Live
100 MW storage in Linn, IA · In queue since August 2021 · Proposed COD June 2025
100 MW
Capacity
1
Components
Battery
4y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 10m
Schedule
9 months past proposed COD
In Study38%
Queue EntryAug 4, 2021
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-06-30
Project Details
State
IA
County
Linn
Region
MISO
Developer
—
Utility
ITC MIDWEST
Entity
MISO
Point of Interconnection
Fairfax 161 kV
Data Source
LBNL + Live