BetaActiveWindMISOLBNL + Live
550 MW generation in Redwood, MN · In queue since August 2021 · Proposed COD September 2024
550 MW
Capacity
1
Components
Wind
4y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 1m
Schedule
19 months past proposed COD
In Study38%
Queue EntryAug 4, 2021
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-09-01
Project Details
State
MN
County
Redwood
Region
MISO
Developer
—
Utility
NORTHERN STATES POWER COMPANY
Entity
MISO
Point of Interconnection
Lyon County 345 kV - Cedar Mountain 345 kV
Data Source
LBNL + Live
No news available for this project.