— Project Summary

Queue ID
MISO-J2099
Capacity
399.03 MW
Technology
Solar
Status
active
Location
Portage, WI
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveSolarMISOLBNL + Live

399.03 MW generation in Portage, WI · In queue since June 2022 · Proposed COD October 2024

399.03 MW

Capacity

1

Components

Solar

3y 9m

In Queue

Cluster Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

2y 4m

Schedule

18 months past proposed COD

Impact Study25%
Queue EntryJun 22, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-10-01

Project Details

State

WI

County

Portage

Region

MISO

Developer

Utility

AMERICAN TRANSMISSION COMPANY

Entity

MISO

Point of Interconnection

Rocky Run to Werner West 345 kV

Data Source

LBNL + Live

No news available for this project.