BetaActiveWindMISOLBNL + Live
200 MW generation in Oliver, ND · In queue since August 2021 · Proposed COD May 2024
200 MW
Capacity
1
Components
Wind
4y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 9m
Schedule
23 months past proposed COD
In Study38%
Queue EntryAug 12, 2021
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-05-01
Project Details
State
ND
County
Oliver
Region
MISO
Developer
—
Utility
MINNESOTA POWER INC.
Entity
MISO
Point of Interconnection
Square Butte East 230 kV
Data Source
LBNL + Live