100 MW hybrid in Montcalm, MI · In queue since November 2021 · Proposed COD September 2024
100 MW
Capacity
1
Components
Solar
4y 4m
In Queue
Cluster Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 10m
Schedule
19 months past proposed COD
Impact Study25%
Queue EntryNov 30, 2021
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-09-01
Project Details
State
MI
County
Montcalm
Region
MISO
Developer
—
Utility
ITC
Entity
MISO
Point of Interconnection
Eureka - Vestaburg 138kV Transmission Line (J1379 POI)
Data Source
LBNL + Live