— Project Summary

Queue ID
MISO-J2044
Capacity
100 MW
Technology
Solar
Status
active
Location
Newton, IN
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveSolarMISOLBNL + Live

100 MW generation in Newton, IN · In queue since March 2022 · Proposed COD September 2024

100 MW

Capacity

1

Components

Solar

4 years

In Queue

Cluster Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

2y 6m

Schedule

18 months past proposed COD

Impact Study25%
Queue EntryMar 29, 2022

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-09-30

Project Details

State

IN

County

Newton

Region

MISO

Developer

Utility

NORTHERN INDIANA PUBLIC SERVICE COMPANY

Entity

MISO

Point of Interconnection

Goodland 138 kV Substation

Data Source

LBNL + Live

No news available for this project.