200 MW generation in Clay, IL · In queue since August 2021 · Proposed COD April 2024
200 MW
Capacity
1
Components
Solar
4y 7m
In Queue
Cluster Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 8m
Schedule
24 months past proposed COD
Impact Study25%
Queue EntryAug 26, 2021
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-04-15
Project Details
State
IL
County
Clay
Region
MISO
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Point of Interconnection
7XENIA - 7MTVERNW 345.0kV
Data Source
LBNL + Live