BetaActiveBatteryMISOLBNL + Live
100 MW storage in Gratiot, MI · In queue since November 2021 · Proposed COD December 2022
100 MW
Capacity
1
Components
Battery
4y 4m
In Queue
Cluster Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
1y 1m
Schedule
40 months past proposed COD
Impact Study25%
Queue EntryNov 15, 2021
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-12-02
Project Details
State
MI
County
Gratiot
Region
MISO
Developer
—
Utility
ITC
Entity
MISO
Point of Interconnection
REGAL
Data Source
LBNL + Live
No news available for this project.