BetaActiveSolarMISOLBNL + Live
200 MW generation in Washington, IA · In queue since August 2021 · Proposed COD March 2024
200 MW
Capacity
1
Components
Solar
4y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 7m
Schedule
25 months past proposed COD
In Study38%
Queue EntryAug 13, 2021
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-03-13
Project Details
State
IA
County
Washington
Region
MISO
Developer
—
Utility
MIDAMERICAN ENERGY CO.
Entity
MISO
Point of Interconnection
SUB T HASKINS
Data Source
LBNL + Live
No news available for this project.