— Project Summary

Queue ID
MISO-J2001
Capacity
220 MW
Technology
Solar
Status
active
Location
Newaygo, MI
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveSolarMISOLBNL + Live

220 MW generation in Newaygo, MI · In queue since August 2021 · Proposed COD May 2025

220 MW

Capacity

1

Components

Solar

4y 7m

In Queue

Cluster Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 9m

Schedule

11 months past proposed COD

Impact Study25%
Queue EntryAug 16, 2021

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-05-01

Project Details

State

MI

County

Newaygo

Region

MISO

Developer

Utility

METC

Entity

MISO

Point of Interconnection

Ludington to Kenowa 345kV

Data Source

LBNL + Live