BetaActiveSolarMISOLBNL + Live
99 MW generation in Columbia, WI · In queue since December 2021 · Proposed COD July 2025
99 MW
Capacity
1
Components
Solar
4y 3m
In Queue
Cluster Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 7m
Schedule
8 months past proposed COD
Impact Study25%
Queue EntryDec 1, 2021
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-07-23
Project Details
State
WI
County
Columbia
Region
MISO
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Point of Interconnection
Columbia - South Fon Du Lac
Data Source
LBNL + Live
No news available for this project.