150 MW generation in Champaign, IL · In queue since March 2022 · Proposed COD October 2025
150 MW
Capacity
1
Components
Wind
4 years
In Queue
Cluster Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 7m
Schedule
6 months past proposed COD
Impact Study25%
Queue EntryMar 24, 2022
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-10-01
Project Details
State
IL
County
Champaign
Region
MISO
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Point of Interconnection
Rantoul East 138kV
Data Source
LBNL + Live