— Project Summary

Queue ID
MISO-J1943
Capacity
200 MW
Technology
Solar
Status
active
Location
Columbia, WI
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveSolarMISOLBNL + Live

200 MW generation in Columbia, WI · In queue since August 2021 · Proposed COD October 2024

200 MW

Capacity

1

Components

Solar

4y 7m

In Queue

Cluster Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 2m

Schedule

18 months past proposed COD

Impact Study25%
Queue EntryAug 23, 2021

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-10-01

Project Details

State

WI

County

Columbia

Region

MISO

Developer

Utility

AMERICAN TRANSMISSION COMPANY

Entity

MISO

Point of Interconnection

N Madison - Columbia 345kV

Data Source

LBNL + Live

No news available for this project.