— Project Summary

Queue ID
MISO-J1934
Capacity
150 MW
Technology
Battery
Status
active
Location
Kenosha, WI
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveBatteryMISOLBNL + Live

150 MW storage in Kenosha, WI · In queue since August 2021 · Proposed COD October 2025

150 MW

Capacity

1

Components

Battery

4y 7m

In Queue

Cluster Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

4y 2m

Schedule

6 months past proposed COD

Impact Study25%
Queue EntryAug 24, 2021

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-10-01

Project Details

State

WI

County

Kenosha

Region

MISO

Developer

Utility

AMERICAN TRANSMISSION COMPANY

Entity

MISO

Point of Interconnection

Lakeview 138kV

Data Source

LBNL + Live

No news available for this project.