150 MW storage in Kenosha, WI · In queue since August 2021 · Proposed COD October 2025
150 MW
Capacity
1
Components
Battery
4y 7m
In Queue
Cluster Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4y 2m
Schedule
6 months past proposed COD
Impact Study25%
Queue EntryAug 24, 2021
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-10-01
Project Details
State
WI
County
Kenosha
Region
MISO
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Point of Interconnection
Lakeview 138kV
Data Source
LBNL + Live
No news available for this project.